OLDER INFORMATION
APRIL 18, 2024
We will start the new storm sewer system installation on Monday, April 22. That work will start just north of the Metra tracks and continue north towards Irving Park Road. You may also see Metra crews moving in/out of the closed roadway as they prepare to replace their signals and build the new pedestrian signal crossing at the railroad tracks.
We will start the new storm sewer system installation on Monday, April 22. That work will start just north of the Metra tracks and continue north towards Irving Park Road. You may also see Metra crews moving in/out of the closed roadway as they prepare to replace their signals and build the new pedestrian signal crossing at the railroad tracks.
APRIL 15, 2024
The Federal Railroad Administration informed us the existing ‘Quiet Crossing’ established at the Metra/CPKC railroad tracks and Rodenburg Road is not valid during the construction of the new roadway. All the rail traffic on these tracks is required to sound their horns as they cross the roadway.
The ‘Quiet Crossing’ will be reinstated when we complete the roadway and install all the safety gear required by the Illinois Commerce Commission and Federal Railroad Administration. We are truly sorry for the inconvenience; neither the Villages nor the designers were aware the ‘Quiet Crossing’ was in jeopardy during construction as the roadway itself is closed to public traffic.
The Federal Railroad Administration informed us the existing ‘Quiet Crossing’ established at the Metra/CPKC railroad tracks and Rodenburg Road is not valid during the construction of the new roadway. All the rail traffic on these tracks is required to sound their horns as they cross the roadway.
The ‘Quiet Crossing’ will be reinstated when we complete the roadway and install all the safety gear required by the Illinois Commerce Commission and Federal Railroad Administration. We are truly sorry for the inconvenience; neither the Villages nor the designers were aware the ‘Quiet Crossing’ was in jeopardy during construction as the roadway itself is closed to public traffic.
APRIL 11, 2024
Rodenburg Road is closed to traffic; pavement removal work continues on Rodenburg Road. You may see Metra crews entering/exiting the closed roadway as they prepare to replace their signals and build the new pedestrian signal crossing at the railroad tracks.
You will see delivery/dump trucks entering the work zone at the north and south ends of the project. Please do not follow those trucks beyond the ‘Road Closed’ signs. The roadway pavement is completely gone; the remaining stone and clay base presents a hazard to passenger vehicles.
Rodenburg Road is closed to traffic; pavement removal work continues on Rodenburg Road. You may see Metra crews entering/exiting the closed roadway as they prepare to replace their signals and build the new pedestrian signal crossing at the railroad tracks.
You will see delivery/dump trucks entering the work zone at the north and south ends of the project. Please do not follow those trucks beyond the ‘Road Closed’ signs. The roadway pavement is completely gone; the remaining stone and clay base presents a hazard to passenger vehicles.
APRIL 4, 2024
We will close Rodenburg Road between Travis Parkway/Timberleaf Circle and Irving Park Road on Friday, April 5. We plan to start our removal work Monday, April 8. You will see crews taking the raised reflector bases off the pavement and dismantling the old guardrail on the north side of the tracks. We will begin removing the old pavement Tuesday morning (April 9). That pavement removal work will continue through the remainder of the week. You may see delivery/dump trucks entering the work zone at the north and south ends of the project. Please do not follow those trucks beyond the ‘Road Closed’ signs. The missing pavement will present a hazard to passenger vehicles.
We will close Rodenburg Road between Travis Parkway/Timberleaf Circle and Irving Park Road on Friday, April 5. We plan to start our removal work Monday, April 8. You will see crews taking the raised reflector bases off the pavement and dismantling the old guardrail on the north side of the tracks. We will begin removing the old pavement Tuesday morning (April 9). That pavement removal work will continue through the remainder of the week. You may see delivery/dump trucks entering the work zone at the north and south ends of the project. Please do not follow those trucks beyond the ‘Road Closed’ signs. The missing pavement will present a hazard to passenger vehicles.
APRIL 3, 2024
We will close Rodenburg Road between Travis Parkway/Timberleaf Circle and Irving Park Road on Friday, April 5. We cannot install the temporary pavement markings with the continuing rains and forecast.
We will close Rodenburg Road between Travis Parkway/Timberleaf Circle and Irving Park Road on Friday, April 5. We cannot install the temporary pavement markings with the continuing rains and forecast.
APRIL 2, 2024
We will close Rodenburg Road between Travis Parkway/Timberleaf Circle and Irving Park Road on Thursday, April 4. We cannot install the temporary pavement markings with the continuing rains and forecast.
We will close Rodenburg Road between Travis Parkway/Timberleaf Circle and Irving Park Road on Thursday, April 4. We cannot install the temporary pavement markings with the continuing rains and forecast.
APRIL 1, 2024
We will close Rodenburg Road between Travis Parkway/Timberleaf Circle and Irving Park Road on Wednesday, April 3. The overnight rains left the pavement too damp to install the temporary pavement markings today; we recognize there is snow in the forecast for Wednesday but are hopeful to get a window of dry pavement early so we can do the work needed to close the roadway.
The posted detour routes traffic along Irving Park Road, Roselle Road and Central Avenue.
We will close Rodenburg Road between Travis Parkway/Timberleaf Circle and Irving Park Road on Wednesday, April 3. The overnight rains left the pavement too damp to install the temporary pavement markings today; we recognize there is snow in the forecast for Wednesday but are hopeful to get a window of dry pavement early so we can do the work needed to close the roadway.
The posted detour routes traffic along Irving Park Road, Roselle Road and Central Avenue.
MARCH 27, 2024
We will close Rodenburg Road between Travis Parkway/Timberleaf Circle and Irving Park Road on Monday, April 1. The closure will likely start during the early morning hours, so please be prepared to follow the detour route if the road closure barricades are in place.
This work is weather-dependent. If we have rains or wet pavement, we cannot install the new lanes lines we need to shift traffic to new lanes. If we must delay, we will use our Village communications teams, message boards and website to provide updates.
The posted detour routes traffic along Irving Park Road, Roselle Road and Central Avenue.
We will close Rodenburg Road between Travis Parkway/Timberleaf Circle and Irving Park Road on Monday, April 1. The closure will likely start during the early morning hours, so please be prepared to follow the detour route if the road closure barricades are in place.
This work is weather-dependent. If we have rains or wet pavement, we cannot install the new lanes lines we need to shift traffic to new lanes. If we must delay, we will use our Village communications teams, message boards and website to provide updates.
The posted detour routes traffic along Irving Park Road, Roselle Road and Central Avenue.
MARCH 21, 2024
We will close Rodenburg Road between Travis Parkway/Timberleaf Circle and Irving Park Road on Monday, April 1. The closure will likely start during the early morning hours, so please be prepared to follow the detour route if the road closure barricades are in place.
The posted detour routes traffic along Irving Park Road, Roselle Road and Central Avenue.
We will close Rodenburg Road between Travis Parkway/Timberleaf Circle and Irving Park Road on Monday, April 1. The closure will likely start during the early morning hours, so please be prepared to follow the detour route if the road closure barricades are in place.
The posted detour routes traffic along Irving Park Road, Roselle Road and Central Avenue.
MARCH 14, 2024
We will close Rodenburg Road between Travis Parkway/Timberleaf Circle and Irving Park Road on Monday, April 1. The closure will likely start during the early morning hours, so please be prepared to follow the detour route if the road closure barricades are in place. You will see signs and message boards in place as reminders starting early next week. The posted detour routes traffic along Irving Park Road, Roselle Road and Central Avenue. We will begin tree removal work and fence removal/relocation work along the Schaumburg Regional Airport frontage on Monday, March 18.
We will close Rodenburg Road between Travis Parkway/Timberleaf Circle and Irving Park Road on Monday, April 1. The closure will likely start during the early morning hours, so please be prepared to follow the detour route if the road closure barricades are in place. You will see signs and message boards in place as reminders starting early next week. The posted detour routes traffic along Irving Park Road, Roselle Road and Central Avenue. We will begin tree removal work and fence removal/relocation work along the Schaumburg Regional Airport frontage on Monday, March 18.
MARCH 7, 2024
Our complete closure of Rodenburg Road between Travis Parkway/Timberleaf Circle and Irving Park Road is expected to begin in early April. We will provide at least two full weeks’ worth of notice before we post the detour and close Rodenburg Road. Expect to see the detour signs and posts installed well in advance of the actual closure. You should be seeing the utility location marks on the ground along Irving Park Road, Roselle Road and Central Avenue. We may begin the tree removal work and fence removal and relocation work along the Schaumburg Regional Airport frontage in the next week or two. We are working with the contractors involved in that work to schedule their teams so we can coordinate those operations.
Our complete closure of Rodenburg Road between Travis Parkway/Timberleaf Circle and Irving Park Road is expected to begin in early April. We will provide at least two full weeks’ worth of notice before we post the detour and close Rodenburg Road. Expect to see the detour signs and posts installed well in advance of the actual closure. You should be seeing the utility location marks on the ground along Irving Park Road, Roselle Road and Central Avenue. We may begin the tree removal work and fence removal and relocation work along the Schaumburg Regional Airport frontage in the next week or two. We are working with the contractors involved in that work to schedule their teams so we can coordinate those operations.
FEBRUARY 29, 2024
We are expecting our complete closure of Rodenburg Road between Travis Parkway/Timberleaf Circle and Irving Park Road to begin in early April. As soon as we lock in the closure start date, we will install message boards/signs and begin notifying local residents. We have contacted the area school districts; both Police and Fire Departments are aware of the closure. Expect to see the detour signs/posts installed well in advance of the actual closure; those signs will be covered until the closure starts. Please see the map for the general limits of the closure and the detour route. We will be maintaining access for the institutions and development from Irving Park to the south.
We are expecting our complete closure of Rodenburg Road between Travis Parkway/Timberleaf Circle and Irving Park Road to begin in early April. As soon as we lock in the closure start date, we will install message boards/signs and begin notifying local residents. We have contacted the area school districts; both Police and Fire Departments are aware of the closure. Expect to see the detour signs/posts installed well in advance of the actual closure; those signs will be covered until the closure starts. Please see the map for the general limits of the closure and the detour route. We will be maintaining access for the institutions and development from Irving Park to the south.
FEBRUARY 22, 2024
We expect our complete closure of Rodenburg Road between Travis Parkway/Timberleaf Circle on the south end and Irving Park Road on the north end to begin in late March/early April. We are working with our contractor’s team to schedule work and define that date. You will see signs and message boards at least two weeks before that closure starts. Our advance work does include tree removal and fence relocation along the Schaumburg Regional Airport’s property. We will install the detour signs well in advance of the closure, but those signs will be covered until the closure starts. When we have that closure start date locked in, we will provide advance notice to residents, institutions and commuters.
We expect our complete closure of Rodenburg Road between Travis Parkway/Timberleaf Circle on the south end and Irving Park Road on the north end to begin in late March/early April. We are working with our contractor’s team to schedule work and define that date. You will see signs and message boards at least two weeks before that closure starts. Our advance work does include tree removal and fence relocation along the Schaumburg Regional Airport’s property. We will install the detour signs well in advance of the closure, but those signs will be covered until the closure starts. When we have that closure start date locked in, we will provide advance notice to residents, institutions and commuters.
FEBRUARY 15, 2024
We are working towards a start day for this year’s work on the Rodenburg Road project. Please do remember that we will be closing the road completely to thru traffic. Once we schedule that closure, you will see detour signs going up and probably some preparation work for fence and tree removal. The closure will extend from north of Travis Parkway/Timberleaf Circle on the south end to Irving Park Road on the north end. There will be no access through the closure; we will be removing then replacing the old roadway. When we have that closure start date locked in, we will provide advance notice to residents, institutions and commuters.
We are working towards a start day for this year’s work on the Rodenburg Road project. Please do remember that we will be closing the road completely to thru traffic. Once we schedule that closure, you will see detour signs going up and probably some preparation work for fence and tree removal. The closure will extend from north of Travis Parkway/Timberleaf Circle on the south end to Irving Park Road on the north end. There will be no access through the closure; we will be removing then replacing the old roadway. When we have that closure start date locked in, we will provide advance notice to residents, institutions and commuters.
DECEMBER 21, 2023
The embankment work is complete. We will be out to monitor the project weekly for a few months, but work is over for the winter. Expect to see us start the next phase of the project sometime after March 1, 2024. When we schedule the closure of Rodenburg, we will resume our regular updates.
The embankment work is complete. We will be out to monitor the project weekly for a few months, but work is over for the winter. Expect to see us start the next phase of the project sometime after March 1, 2024. When we schedule the closure of Rodenburg, we will resume our regular updates.
DECEMBER 14, 2023
The ground improvement work is complete. Crews started installing the new embankments that will raise the new roadway to the final elevations. Expect that work to continue through next week.
The ground improvement work is complete. Crews started installing the new embankments that will raise the new roadway to the final elevations. Expect that work to continue through next week.
DECEMBER 7, 2023
The concrete column installation is complete. The vertical wick drain installation is finished on the west side of the roadway and will continue on the east side of Rodenburg through early next week. Once this ground improvement work is finished, we will start installing the new embankments that will help raise the roadway to the final elevations.
The concrete column installation is complete. The vertical wick drain installation is finished on the west side of the roadway and will continue on the east side of Rodenburg through early next week. Once this ground improvement work is finished, we will start installing the new embankments that will help raise the roadway to the final elevations.
NOVEMBER 30, 2023
The concrete column installation started this week and should wrap up Friday, December 1. We will move to vertical wick drain installation on the west side of the road early next week. When we have completed that work and given the concrete columns some time to solidify, we will move back to the east side of the roadway. Once this ground improvement work is finished, we will start installing the new embankments that will help raise the roadway to the final elevations. ComEd’s team completed work on their underground vault at Timberleaf Circle North this week and will open Timberleaf Circle North Monday, December 4.
The concrete column installation started this week and should wrap up Friday, December 1. We will move to vertical wick drain installation on the west side of the road early next week. When we have completed that work and given the concrete columns some time to solidify, we will move back to the east side of the roadway. Once this ground improvement work is finished, we will start installing the new embankments that will help raise the roadway to the final elevations. ComEd’s team completed work on their underground vault at Timberleaf Circle North this week and will open Timberleaf Circle North Monday, December 4.
NOVEMBER 21, 2023
The vertical wick drain installation should start right after the holiday weekend. We expect the work to start with the installation of concrete support columns on the east side of the road. ComEd’s team is finishing up work at the vault at Timberleaf Circle North. We expect to see them fill in the area around the vault with stone and temporary concrete next week. They will remove their equipment and open the roadway to traffic.
The vertical wick drain installation should start right after the holiday weekend. We expect the work to start with the installation of concrete support columns on the east side of the road. ComEd’s team is finishing up work at the vault at Timberleaf Circle North. We expect to see them fill in the area around the vault with stone and temporary concrete next week. They will remove their equipment and open the roadway to traffic.
NOVEMBER 16, 2023
The vertical wick drain installation should start in the next few weeks. We are working with ComEd to confirm a few dates so we can safely install the drains near the aerial lines along the west side of Rodenburg. ComEd’s team moved to their underground vault at Timberleaf Circle North this week. They will have Timberleaf Circle North closed completely during their workdays and open to one lane of traffic to exit westbound overnight and on weekends.
The vertical wick drain installation should start in the next few weeks. We are working with ComEd to confirm a few dates so we can safely install the drains near the aerial lines along the west side of Rodenburg. ComEd’s team moved to their underground vault at Timberleaf Circle North this week. They will have Timberleaf Circle North closed completely during their workdays and open to one lane of traffic to exit westbound overnight and on weekends.
NOVEMBER 8, 2023
The vertical wick drain installation should start Monday, November 13. These drains help water migrate out of the soils below the new roadway and multi-use path as we add embankment. The new roadway base will compress the soils below and force water up and out. We will also install a series of concrete grout columns along the east side of Rodenburg to further support the new embankments. Once those two tasks are done, you will see trucks filled with clay embankment material and compaction equipment as we build those new slopes. ComEd’s team moved to their underground vault at Timberleaf Circle North this week. They will have Timberleaf Circle North closed completely during their workdays and open to one lane of traffic to exit westbound overnight and on weekends.
The vertical wick drain installation should start Monday, November 13. These drains help water migrate out of the soils below the new roadway and multi-use path as we add embankment. The new roadway base will compress the soils below and force water up and out. We will also install a series of concrete grout columns along the east side of Rodenburg to further support the new embankments. Once those two tasks are done, you will see trucks filled with clay embankment material and compaction equipment as we build those new slopes. ComEd’s team moved to their underground vault at Timberleaf Circle North this week. They will have Timberleaf Circle North closed completely during their workdays and open to one lane of traffic to exit westbound overnight and on weekends.
NOVEMBER 2, 2023
We have completed the working platforms on the east and west sides of Rodenburg. Our next steps involve the installation of vertical ‘wick’ drains to help water migrate out of the soils below the new roadway and multi-use path as we add embankment. The new roadway base will compress the soils below and force water up and out. We expect to see the ground improvement team on site with their larger equipment sometime after November 6.
ComEd’s team moved to their underground vault at Timberleaf Circle North this week. They will have Timberleaf Circle North closed completely during their workdays and open to one lane of traffic to exit westbound overnight and on weekends.
We have completed the working platforms on the east and west sides of Rodenburg. Our next steps involve the installation of vertical ‘wick’ drains to help water migrate out of the soils below the new roadway and multi-use path as we add embankment. The new roadway base will compress the soils below and force water up and out. We expect to see the ground improvement team on site with their larger equipment sometime after November 6.
ComEd’s team moved to their underground vault at Timberleaf Circle North this week. They will have Timberleaf Circle North closed completely during their workdays and open to one lane of traffic to exit westbound overnight and on weekends.
OCTOBER 26, 2023
Expect to see a few days of work along the west side of Rodenburg to complete the working platform for the ground improvements contractor over the next week. We expect to see that team with their larger equipment sometime after November 6. We will continue to have daily lane closures, so please use extra caution in our work zone. ComEd’s team will move from the vault just north of the tracks to the vault at Timberleaf Circle North early next week. They will likely have Timberleaf Circle North closed completely during their workdays and reopen for overnight and weekends to one-lane traffic to exit westbound.
Expect to see a few days of work along the west side of Rodenburg to complete the working platform for the ground improvements contractor over the next week. We expect to see that team with their larger equipment sometime after November 6. We will continue to have daily lane closures, so please use extra caution in our work zone. ComEd’s team will move from the vault just north of the tracks to the vault at Timberleaf Circle North early next week. They will likely have Timberleaf Circle North closed completely during their workdays and reopen for overnight and weekends to one-lane traffic to exit westbound.
OCTOBER 19, 2023
Even with more than three inches of rainfall at the end of last week, we have seen some progress. We have completed the ground improvement platform along the east side of Rodenburg. This is the base that the ground improvements contractor will use to install drains and support columns. We have moved to the west side to build the same type of platform there. We will continue to have daily lane closures to support this work. Please use extra caution in our work zone. ComEd’s teams continue rebuilding an underground vault just north of the tracks; when they finish that work, they will move to the vault at Timberleaf Circle North.
Even with more than three inches of rainfall at the end of last week, we have seen some progress. We have completed the ground improvement platform along the east side of Rodenburg. This is the base that the ground improvements contractor will use to install drains and support columns. We have moved to the west side to build the same type of platform there. We will continue to have daily lane closures to support this work. Please use extra caution in our work zone. ComEd’s teams continue rebuilding an underground vault just north of the tracks; when they finish that work, they will move to the vault at Timberleaf Circle North.
OCTOBER 12, 2023
We have completed most of the excavation work along the east side of Rodenburg. You can see the beginnings of the working platform that the ground improvements contractor will use to install drains and support columns. We will continue to have daily lane closures to support this work. Please use extra caution in our work zone. ComEd’s teams continue rebuilding an underground vault just north of the tracks; when they finish that work, they will move to the vault at Timberleaf Circle North.
We have completed most of the excavation work along the east side of Rodenburg. You can see the beginnings of the working platform that the ground improvements contractor will use to install drains and support columns. We will continue to have daily lane closures to support this work. Please use extra caution in our work zone. ComEd’s teams continue rebuilding an underground vault just north of the tracks; when they finish that work, they will move to the vault at Timberleaf Circle North.
OCTOBER 5, 2023
We are starting the excavation work along the east side of Rodenburg. You will see us excavate out the unsuitable topsoil and begin the installation of the stone and gravel platform we will use to install the ground improvements. ComEd’s teams continue rebuilding an underground vault just north of the tracks; when they finish that work, they will move to the vault at Timberleaf Circle North.
We are starting the excavation work along the east side of Rodenburg. You will see us excavate out the unsuitable topsoil and begin the installation of the stone and gravel platform we will use to install the ground improvements. ComEd’s teams continue rebuilding an underground vault just north of the tracks; when they finish that work, they will move to the vault at Timberleaf Circle North.
SEPTEMBER 28, 2023
The utility contractors completed their most important relocation work this week. We may have to ask ComEd to relocate one more pole, but we are working together with the utility and the contractor to avoid that. One last telecommunications team needs to relocate their cables on the west side of Rodenburg. ComEd’s teams continue rebuilding an underground vault just north of the tracks. When they finish that work, they will move to the vault at Timberleaf Circle North.
The utility contractors completed their most important relocation work this week. We may have to ask ComEd to relocate one more pole, but we are working together with the utility and the contractor to avoid that. One last telecommunications team needs to relocate their cables on the west side of Rodenburg. ComEd’s teams continue rebuilding an underground vault just north of the tracks. When they finish that work, they will move to the vault at Timberleaf Circle North.
SEPTEMBER 21, 2023
The utility contractors continue working diligently to relocate their facilities. ComEd will be back on the project Tuesday and Wednesday, September 26 and 27, to relocate poles along the west side of the road. Telecom teams are working to splice their new fiber optic lines together at a few locations along the project. You will also see teams rebuilding two ComEd underground vaults, one at Timberleaf Circle North and one just north of the railroad tracks.
The utility contractors continue working diligently to relocate their facilities. ComEd will be back on the project Tuesday and Wednesday, September 26 and 27, to relocate poles along the west side of the road. Telecom teams are working to splice their new fiber optic lines together at a few locations along the project. You will also see teams rebuilding two ComEd underground vaults, one at Timberleaf Circle North and one just north of the railroad tracks.
SEPTEMBER 14, 2023
Our utility partners are working diligently to relocate their facilities to clear the way for the project’s work. Expect to see the ComEd poles along the west side of the road south of the tracks move a bit further west. Telecom teams will continue to install new underground ducts. You will also see teams rebuilding two ComEd underground vaults, one at Timberleaf Circle North and one just north of the railroad tracks.
Our utility partners are working diligently to relocate their facilities to clear the way for the project’s work. Expect to see the ComEd poles along the west side of the road south of the tracks move a bit further west. Telecom teams will continue to install new underground ducts. You will also see teams rebuilding two ComEd underground vaults, one at Timberleaf Circle North and one just north of the railroad tracks.
SEPTEMBER 12, 2023
This project will reconstruct Rodenburg Road in Schaumburg from Irving Park Road to the Village limits; in Roselle, the project will reconstruct the pavement from the Village limits to Timberleaf Circle and resurface the pavement from Timberleaf Circle to Central Avenue.
Click here to view the project brochure.
This project will reconstruct Rodenburg Road in Schaumburg from Irving Park Road to the Village limits; in Roselle, the project will reconstruct the pavement from the Village limits to Timberleaf Circle and resurface the pavement from Timberleaf Circle to Central Avenue.
Click here to view the project brochure.